What is the difference between a construction lien and a mechanics lien?

There are two major differences between a construction lien and a mechanic’s lien. One is the people who may place these liens, and the other is the priority that lien has if it’s competing with other claims against the home or commercial space.

How do I file a construction lien in Washington state?

How to File a Mechanic’s Lien in Washington State – Step-By-Step Guide

  1. Step 1: Determine if you have the right to file a lien.
  2. Step 2: Prepare the lien document.
  3. Step 3: File the lien.
  4. Step 4: Send notice of lien.
  5. Step 5: Secure payment.
  6. Step 6: Release the lien.


How do you put a lien on a house in Idaho?

A Claim of Lien must be filed containing a statement of the claimant’s demand, the names of relevant parties, and a property description. It must be verified by the oath of the claimant and a copy must be served personally or by certified mail to the property owner. Idaho Code § 45-507.

How long is a mechanics lien good for in Washington State?

8 months

How long does a lien last in Washington? In Washington, a mechanics lien is effective for 8 months after its filing, and an action to enforce must be initiated within that period of time. If this 8-month timeline passes without an action being filed to enforce the lien, the lien expires.

How long does a lien stay on your property in Washington state?

ten years

How long does a judgment lien last in Washington? A judgment lien in Washington will remain attached to the debtor’s property (even if the property changes hands) for ten years.

How long does a lien stay on your property in Idaho?

A tax lien is valid for five years unless a continuation is filed before it expires. The continuation extends the lien another five years. Continuations can be filed repeatedly, which could make a tax lien valid indefinitely. Idaho law allows continuations on state liens until they’re paid in full.

How long does a mechanics lien last in Idaho?

6 months

An Idaho mechanics lien generally stays effective for 6 months from the date on which it was recorded.

Do liens expire in Idaho?

A lien arising from an order for restitution to a crime victim where the order of restitution has been recorded as a judgment pursuant to section 19-5305, Idaho Code, continues until twenty (20) years from the date of the judgment, unless the judgment be previously satisfied, or unless the judgment is stayed or set

How do I get rid of a lien in Washington state?

The process in Washington state is rather simple. The “lien release” direction is provided by state, in R.C.W. § 60.04.



Need to cancel your mechanics lien?

  1. The recorded lien’s identifying information;
  2. A statement that the lien is requested to be released; and.
  3. The statement must be notarized.


Can an unlicensed contractor file a lien in Washington?

In California and Washington, the laws against unlicensed contractors are very strict — unlicensed contractors have no recovery rights whatsoever. This means they cannot file a lien, or a lawsuit, or anything at all.

How long does a contractor have to file a lien in Washington state?

A lien against a consumer must be filed within 90 days of work stoppage, or delivery of materials. Additional information regarding the timeline for filing liens may be found in RCW 60.04. 091.

How long do you have to file a lien in Washington state?

within 90 days

When can a lien be filed against you? A lien against a consumer must be filed within 90 days of work stoppage, or delivery of materials. Additional information regarding the timeline for filing liens may be found in RCW 60.04. 091.

Can an unlicensed contractor file a lien in Washington state?

In California and Washington, the laws against unlicensed contractors are very strict — unlicensed contractors have no recovery rights whatsoever. This means they cannot file a lien, or a lawsuit, or anything at all.

Who can put a lien on a property?

According to the Daily Herald, the only people who can place a lien on your home are those who have done work or otherwise contributed to the value of your home. For example, contractors and suppliers could place a lien if you do not pay them. Other creditors, though, usually cannot put a lien on your property.

How long after completion can a contractor file a construction lien Oregon?

within 75 days

Under Oregon law, a contractor or subcontractor must file a construction lien within 75 days “after the person has ceased to provide labor, rent equipment or furnish materials or 75 days after completion of construction, whichever is earlier.” ORS 87.035(1).

How long does a mechanics lien last in Oregon?

120 days

In Oregon, a mechanics lien only lasts for 120 days after the date the claim was filed. If an enforcement (foreclosure) action isn’t initiated within this timeline, the claim expires and will no longer be enforceable.

Who can file a construction lien in Oregon?

Liens are usually filed by one of your general contractor’s subcontractors, employees, material suppliers, or equipment rental companies, because the general contractor did not pay for the work performed, materials supplied, or equipment rented. Your general contractor may file a lien if you have not paid him or her.